Realizacje

Construction of a new cargo base at Katowice Airport in Pyrzowice

Nawierzchnia betonowa

The task consisted in the extension of aprons at Katowice Airport in Pyrzowice with an area of approx. 54,650.00 m2

As part of the task, we carried out:

– placement of a top layer of C40/50 cement concrete, thickness: 30cm

– installation of dowels and baskets

– reinforcement of the aprons according to the Technical Documentation, using materials supplied by the General Contractor

– provision of compressible inserts (polystyrene + metal sheet) at expansion gaps, where the laying process was carried out without interruption of production

– installation of manhole reinforcements from material provided by the General Contractor

– surface work carried out using SOMERO S -22 EZ, WIRTGEN SP 850 AND SWEPAC machines

Project duration: September – December 2020

                           September – December 2021